A Woman-owned business enterprise

 

Senior Estimator/Project Managers Stanley Hurd along with David Harwood have spearheaded this project.

 

The company had employees working onsite as well as remotely in Jacksonville Florida, where the precast cells were constructed. 


This CCDC Project required extensive implementation of 3-D AutoCAD drawings handled by David Harwood and our design team.


the largest capital improvement project in chatham county history



Complete Electrical installation for the new  $90 million - 330,000 square-foot expansion of the Chatham County Detention Center in Georgia.


Sixty-six percent of the site preparation and construction work went to local subcontractors.  We proudly made up a substantial portion of the local participation for this project.  Construction took 3 years to complete.


 

chatham county detention center expansion